STOPPING TH

The supply chain problem civil engineering keeps inheriting. By Neeral Shah, Founder and CEO, YardLink

Civil engineering projects are all about keeping on schedule. A night closure on a major road has a fixed window. If the excavator booked for ten o’ clock arrives at half past one, nobody gets those hours back. Traffic management is still deployed. The crew is still paid. The programme still slips a shift. And the decision that caused it, made weeks earlier by someone choosing a supplier on a cheap day rate, is long forgotten by the time anyone counts the cost.

That is how supply chain failure works. It arrives as a late delivery, a missed collection, a waste carrier with the wrong paperwork.
Each one is small enough to absorb. Together, they quietly decide whether a project is profitable.
The cost nobody sees coming
We have managed procurement data across more than 19,000 projects, and the pattern is consistent: the cost of a failure is far higher than it first appears.
A failed or delayed delivery costs between £ 750 and £ 800 once labour and programme impact are properly accounted for. Across a site over the life of a project, that adds up to around £ 15,000 in lost productivity.